Commissioning, testing gensets using resistive/reactive load banks

11/12/2013


The case for reactive load bank testing

The ability to simulate varying reactive loads, which are more realistic, is the most essential benefit for a load bank that provides both kVA (resistive) and kVAR (reactive) loads. The critical differences between testing with a resistive-only load bank and a resistive/reactive load bank are compared in Table 1. A resistive-only load bank can provide adequate testing of the individual prime mover and load sharing (including load add/load shed) controls of a multiple unit facility. However, a reactive load bank allows testing of the alternator, load sharing, and transient responses because it can apply loads that approach those experienced during normal genset operation (see Table 2). 

Genset engine governors respond to loads by reducing engine speed. Figure 2 compares the transient response for a large diesel standby genset when applying a block load using restive-only and resistive/reactive load banks. The resulting initial synchronous voltage dip (Vdip1) using the 75% load at 0.80 power factor results in a voltage dip that is approximately 25% greater when compared to the equivalent resistive-only load applications. The engine speed related voltage dip (Vdip2) is similar, in both cases, due to the manufacturer’s standard V/Hz-type voltage regulator. 

During testing with a resistive-only load bank, a system that is sensitive to transient voltage dips would not necessarily provide an indication of a power supply or system condition that would lead to a potential problem during operation. Solid-state controls and power supplies are particularly sensitive to transients and can shut down unexpectedly during load changes unless specifically backed up with a dedicated power source capable of riding through the voltage and frequency transients associated with block loading of the gensets. 

Figure 2: This graph compares the transient response for a large diesel standby genset when applying a block load using restive-only and resistive/reactive load banks. Courtesy: HPS Loadbanks (Data source: Caterpillar Engine Sizer program)When testing multiple unit generator systems, the ability to share reactive loads (kVAR) equally is critical to achieving the maximum-rated power system output. When load sharing controls are not properly configured (i.e., droop settings, cross-current compensation, and measurement and control device polarities), resistive-only testing can fail to determine how the reactive load is accepted by an individual generator. In addition, the paralleling switchgear and protective relays may perform adequately under resistive load applications, but the reactive load bank testing will provide load acceptance and rejection that simulates real-world conditions more closely (see Figure 3). 

Choosing the right resistive/reactive load bank

When selecting a resistive/reactive load bank it is important to consider key features including ease of operation, onboard diagnostics, metering, the ability for an operator to control multiple units from a single controller, and data download capabilities. Load banks offering automatic step loading and duration, and data collection and reporting capabilities are beneficial in providing the necessary records to demonstrate compliance with the facility and regulatory requirements. 

Connecting load banks to a facility normally involves temporarily connecting the 3-phase power conductors to the load bus. Electrical testing and load bank rental companies can supply the necessary load banks, transformers, and cables to provide the correct service voltage for the equipment being tested. 

The proof is in the testing

Figure 3: This drawing shows the components used for a typical load test at a large facility. Courtesy: HPS LoadbanksSpecifying engineers can and should promote reactive load bank testing because it is the best way to test the entire system to identify system-wide weaknesses during commissioning and at periodic test intervals to be in compliance with the regulatory agencies. Without proof of testing, the design remains hypothetical. Testing systems with the correct size and type of resistive/reactive load bank validates the power generation system design (see Table 3). 

For existing installations, proper reactive load bank testing provides real-time data and factual evidence of reliability, functionality, and reduction of capacity resulting from aged equipment. Additionally, reactive load bank testing provides a best-case simulated real-world condition where voltage-drop, thermal heating, harmonics, and efficiency can be analyzed more effectively than with a resistive load only. 

Full system integration testing of critical systems during commissioning establishes an accurate baseline for ongoing operational performance and is a valuable tool in providing a higher level of confidence in the emergency power system.


<< First < Previous 1 2 Next > Last >>

Anonymous , 12/12/13 10:26 PM:

Great article - knowing that one can use reactive load banks to simulate aging systems to see their performance is a eye opener.
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.