Commissioning solves operational issues, saves energy

In this HVAC commissioning project, the engineering team saved money and energy at an existing telecom equipment building.

03/19/2014


Figure 1: This control schematic shows a chilled water plant with variable primary flow and redundant pumps. Courtesy: expOne of the most significant ASHRAE Standard 90.1-2010 updates was the requirement for HVAC commissioning on most projects greater than 50,000 sq ft. The U.S. Green Building Council’s LEED Energy and Atmosphere perquisite 1 (EAp1) requires fundamental commissioning of building energy systems.

Most chiller plant and fan system commissioning can produce energy savings that can pay off in six months to two years and create value for the owner for the entire life of the equipment. The payback is even quicker for facilities that operate 24x7, like hospitals, data centers, 911 centers, telecom equipment buildings, and others.

Our engineering firm validated the significance of commissioning during an HVAC commissioning project at an existing telecom equipment building in Illinois. The owner didn’t have a commissioning plan and invited the design team to perform acceptance commissioning (carry out functional performance tests on HVAC systems). The building is more than 20 years old with gross floor area of approx. 350,000 sq ft. It has three floors including basement. Half of the building houses telecom equipment like switches, transport equipment, a rectifier plant, and a battery plant, which require cooling for 8,760 hours in a year. This is a low heat density environment, and a traditional air handling unit (AHU) with distribution ductwork is able to cool the equipment. The other half of the building consists of offices for support staff. Most of the offices are vacant and currently served by an existing system independent of the system serving telecom equipment.

The need for commissioning

In the HVAC system upgrade project, for which construction was completed a year ago, a new chiller plant and air handlers were added to the building. The HVAC equipment was dedicated for cooling telecom equipment. One year after the substantial completion and start-up, the design team was called to commission the project and solve the following maintenance issues:

  • The chiller would shut down on low flow several times a week and would generate an alarm.
  • The chiller plant was designed to operate with one pump (the second pump was designed as a redundant pump), but the maintenance team was operating both pumps together to avoid tripping of the chiller on low flow.
  • When the pump’s variable frequency drive (VFD) was manually put on bypass mode, it would overload and the motor would become hot. Eventually, the motor would trip on high temperature.
  • Maintenance was also experiencing high humidity in the telecom equipment space.

Figure 2: This pump curve shows final the commissioned point versus full load design point. The full load design point corresponds to future load growth in the building. Courtesy: Bell & Gossett, a Xylem BrandThe new cooling equipment consists of a central chiller plant and AHUs. The chiller plant consists of one 90-ton packaged air cooled chiller, two chilled water pumps (primary and redundant), two chilled water cooling coils (one at each air handler), and pressure-independent valves at each cooling coil and bypass. The chiller plant is designed as variable primary system (see Figure 1).

AHU-1-1 and AHU-2-1 have a chilled water cooling coil and 100% outside air economizer. The outside air economizer provides free cooling whenever ambient temperature and humidity allow. AHU-1-1 is located on the first floor and serves the basement and first floor. AHU-2-1 is located on the second floor and serves only the second floor. The air handlers are equipped with high-efficiency filters.

The chiller plant and air handlers were oversized for future capacity. The building owner was expecting to double the load in the building over the next five years and wanted the engineer to design the system for ultimate future capacity. The HVAC system upgrade was a large capital expense, and the owner wanted it to serve current as well as future needs.

Figure 3: In this pump curve, the pump overloading point is shown, which caused tripping of the pump motor due to overflow. Clearly, overflow was cause of pump overheating and tripping. Courtesy: Bell & Gossett, a Xylem BrandCommissioning, troubleshooting

The design team carefully reviewed, measured, and tested data including air- and water-side tests and balance reports. The team also reviewed the BAS logs and trends, and visited the site to find following operational issues:

  • The chiller differential pressure (DP) switch that monitors the minimum flow through the chiller was set for the full design flow (189 gpm), as opposed to minimum flow as specified by the manufacturer (100 gpm).
  • Chilled water pumps were controlled to maintain 18 psi across the most remote AHU coil pressure-independent valve, as opposed to 5 psi required by design. This was unnecessarily pressurizing the system and wasting pump energy.
  • The flowmeter controlling the bypass valve was not calibrated and was calling for the bypass valve to open 100% of the time. The flowmeter was controlled to maintain full design flow through the system at all times.
  • The chiller was seeing delta T of 3 F. The chiller plant was suffering from low delta T syndrome.
  • During bypass mode, the pump would ride so low on the pump curve that it would overload and trip the motor.
  • The air handler supply air temperature was in the range of 64 to 67 F. This gave very little opportunity for de-humidification, resulting in high space humidity (62% to 65% relative humidity, RH).

To resolve these issues and save a substantial amount of energy, the following steps were taken in a sequential manner while carefully observing system performance over two days:

  1. The chiller DP switch was replaced. DP on the switch was set to flow corresponding to the minimum flow-through chiller as specified by the manufacturer (100 gpm).
  2. Chiller water pumps were now controlled to maintain 5 psi across the most remote AHU coil pressure-independent valve as required by the design.
  3. The flowmeter was calibrated and the bypass valve was set to maintain 100 gpm through the chiller.
  4. With these changes, the engineering team was able to run the chiller plant with only one pump operating. As a bonus, the pump didn’t trip the VFD, which was put on bypass because it would never ride that low on the pump curve (see Figure 2).
  5. The air handler supply fans were ramped down to 60% and 65% of full speed using a VFD. This dropped the supply air temperature to 58 to 59 F and space humidity to 54% to 55% RH.

Table 1: In this calculation, pump and fan energy savings are calculated using fan and pump afinity laws. Courtesy: exp

Energy savings

The above measures not only solved all operational issues, but also created significant energy savings for the owner. The energy savings from pumps and fans were calculated to be $8,163 per year. This also represents the lost energy savings potential because commissioning was delayed by almost a year. The total cost for commissioning was $5,800. This results in a simple payback of 8.5 months. If these issues were not addressed, the owner would have spent an additional $163,263 over the life of equipment (20 years), without considering any increases in utility costs and interest rates.

Commissioning is one of the most complex and important parts of building construction. ASHRAE 90.1-2010 has mandated it on all HVAC systems in commercial buildings larger than 50,000 sq ft, and it is also a prerequisite in LEED v3. It is widely recognized and proven that commissioning pays back in less than two years—and often sooner.

The owner was delighted with the results of the HVAC commissioning at the end of the project. The building owner has a policy of actively pursuing energy savings projects that pay back in less than two years. It was also a big boost for the commissioning team, which also served as the design team in this case.


Sushil Kumar is a project manager and senior mechanical engineer with exp US services Inc., Chicago.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.