China power plant to have two ultra-supercritical units added

Addition of new units are designed to help plant in central China contribute to economic development and improved grid stability

11/04/2011


 Two new 1,000-MW, ultra-supercritical power generating units under construction at the China Resources Puqi power plant, and Emerson Process Management will install its Ovation expert control system. The contract was awarded by China Resources Power Holdings Company Ltd., owner of the plant.

The power plant is located in China’s Hubei province, near the Yangtze River. It currently consists of two 600-MW, coal-fired units that have utilized Ovation technology since they went into service in 2004. The new ultra-supercritical units, which are expected to begin commercial operation in the second half of 2012, are designed to contribute to the region’s economic development and improved grid stability by offsetting megawatts lost when existing hydro-electric power stations are unable to meet demand.

As part of its automation solution at Puqi, Emerson will supply a total of 64 redundant Ovation controllers and 23 workstations. An Ovation system at each unit will perform data acquisition as well as monitor and control the boiler and turbine supplied by Shanghai Electric Group. Unifying boiler and turbine controls provides improved unit stability, responsiveness and thermal efficiencies; tighter overall control of plant operations; and a clearer view of key plant and turbine parameters.

The technology will also manage each unit’s modulating control system, sequence control system, electrical control system, furnace safety supervisory system, feedwater turbine control system and balance-of-plant processes. In addition, Ovation will monitor and control systems common to both units using multi-networking technology. In all, the Ovation control systems will manage approximately 26,100 I/O points.

www.emersonprocess.com

Emerson Process Management

- Edited by Chris Vavra, Control Engineering, www.controleng.com 



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. The 2012 Top Plant winners have been named.
In 2012, Plant Engineering's Product of the Year program will celebrated its 25th anniversary. Read about the 2012 winners and nominate for 2013.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2012 Leaders here.
Find the fake! Counterfeit electrical equipment a clear and present danger
Investment in excellence: One plant's improved productivity and quality was repaid when their company expanded the facility
Strategic uptime, Increased capacity goes right to the bottom line
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Alarm management tips, Power management, Building automation
Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Attacking Energy Costs: Strategies for showing financial return on energy management investments

2012 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results


Poll of the Week

What category most helps you select new products?
Recommendation from colleagues
Product of the Year winners
Supplier information
Trade show visit


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.