Blowout preventer not tested to shear pipe

The blowout preventer that failed to stop last year’s Gulf of Mexico oil spill hadn’t been tested to see if it could cut through a bent drill pipe, said a senior official of the company that made the device.

By Gregory Hale; Source: ISS Source

04/26/2011


The blowout preventer that failed to stop last year’s Gulf of Mexico oil spill hadn’t been tested to see if it could cut through a bent drill pipe, said a senior official of the company that made the device.

The firm hired by the government to examine the 300-ton device after they brought it up from the seafloor concluded the blind shear rams couldn’t pinch the well shut by cutting through the drill pipe. That’s because the pipe was off center. The firm faulted the design of the Cameron-made blowout preventer.

Cameron vice president David McWhorter told a federal investigative panel he couldn’t say if the company designed the device to cut through a bent drill pipe. He said it did not undergo testing for that possibility before the disaster.

“I am not going to hazard an opinion,” said McWhorter, who works in Cameron’s division that handles engineering and quality for drilling systems.

The testimony wrapped up the seventh series of hearings before the joint U.S. Coast Guard-Bureau of Ocean Energy Management Regulation and Enforcement panel, which is investigating the causes of the Deepwater Horizon rig explosion off Louisiana last April 20. The blast killed 11 workers and led to the worst offshore oil spill in U.S. history.

The panel should release a preliminary statement within the next few weeks and will issues a full report in July.

In earlier testimony, Ralph Linenberger, a BP consultant hired to monitor the blowout preventer examination on behalf of the company, questioned the findings of testing firm Det Norske Veritas. Among other things, he said he did not see evidence the drill pipe had buckled, as DNV concluded it had.

“It looked fairly straight to me,” Linenberger said.

He also said DNV did not conduct any substantive testing that would look at the possibility of maintenance of the blowout preventer being a potential factor in the device’s failure.

Transocean owned the rig that exploded and was responsible for maintaining the blowout preventer. BP was leasing the rig from Transocean and owned the undersea well that blew out.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. The 2012 Top Plant winners have been named.
In 2012, Plant Engineering's Product of the Year program will celebrated its 25th anniversary. Read about the 2012 winners and nominate for 2013.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2012 Leaders here.
Investment in excellence: One plant's improved productivity and quality was repaid when their company expanded the facility
Strategic uptime, Increased capacity goes right to the bottom line
2013 Forecast Issue: A shift in manufacturing
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Alarm management tips, Power management, Building automation
Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Attacking Energy Costs: Strategies for showing financial return on energy management investments

2012 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results


Poll of the Week

What category most helps you select new products?
Recommendation from colleagues
Product of the Year winners
Supplier information
Trade show visit


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.