Achieving daylighting credits for LEED

06/20/2013


Creating the simulation and analysis 

Simulation details include several items: 

Site location:

  • The building is located in Northwest Chicago, Illinois. By closest approximation, the daylight model was located at a latitude 42 deg north and longitude 88 deg west.
  • All of the assessment results in this study were conducted on an analysis plane positioned 30 in. above each finished floor. The date and times for the simulation were set on Sept. 21 (fall equinox) at 9 a.m. and 3 p.m.
  • The luminance sky distribution set in AGi32 lighting simulation software was clear sky. 

Table 1: Surface properties. Courtesy: expSurface properties: The visible light reflecting properties of the internal surface finishes and transmission properties of the glazing for the individual spaces were assigned according to the surface finish and glazing schedule provided by architects (see Table 1). 

Space classification: The following are selected as regularly occupied areas (as defined by USGBC) because they are spaces where one or more individuals normally spend time (more than 1 hour per person per day on average) seated or standing as they work, study, or perform other focused activities inside a building. 

Daylighting analysis, including:

  • Building spaces: The combined floor area of the regularly occupied spaces in the building is approximately 1462 sq ft. Most of the regularly occupied offices in the building mainly face south or east. They receive direct daylight during the evaluation time and therefore have the highest daylight levels of the offices in the building.
  • Iso-contour plan and calculation summary (see Figure 1). 

Achieving the goal 

The daylight levels for all regularly occupied spaces were assessed individually for Sept. 21 at 9 a.m. and 3 p.m. using architectural drawings and schedules for the opaque surface finishes and glazing. The sun position and sky distribution required for analyzing the probability of achieving LEED daylight and views credit is a good criterion for evaluating the overall daylighting performance because the sun is at low angles and it is a mid-season sun.

The daylighting performance of the prototype building is balanced with even daylight distribution. All the spaces analyzed were comprised of relatively small floor areas. In this example, the daylight analysis results show the building has 85% of the regularly occupied space floor area of 25 to 500 fc at 9 a.m. and 75% at 3 p.m. Because this result meets the minimum requirement for the LEED EQc8.1: Daylight and Views - Daylighting credit, the proposed design is anticipated to achieve 1 point for this credit.


Siva Haran is a senior electrical engineer and project manager at exp. He is an advisory member of Sustainable Lighting Committee of IES. He has extensive experience in designing lighting and electrical systems for commercial, institutional, light industrial, and residential projects.

See tips for analyzing daylighting, as well as a glossary/definitions below.


<< First < Previous 1 2 3 Next > Last >>

No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.