Achieving daylighting credits for LEED

Learn the steps to achieve points for the U.S. Green Building Council LEED EQc8.1: Daylight and Views – Daylight credit.

06/20/2013


Learning objectives

  1. Understand the U.S. Green Building Council LEED criteria for daylighting credit.
  2. Learn to use modeling software to conduct a daylighting analysis.  
  3. Learn to document and use the results of an analysis. 

The use of naturally lighted spaces is a valuable strategy for achieving energy savings and earning U.S. Green Building Council (USGBC) LEED credits. Beyond energy savings, careful use of daylighting can contribute to occupant well-being and productivity. Consequently, architects and engineers are encouraged to improve their ability to apply daylighting strategies to building design solutions. 

The USGBC, which administers the LEED green building rating system, has several design elements to achieve points. Daylighting is one of them. The primary standard of reference, of course, is the LEED 2009 Reference Guide for New Construction and Major Renovations

Under LEED EQc8.1: Daylight and Views – Daylight, the intent is to provide building occupants with a connection between indoor spaces and the outdoors through the introduction of daylight into the regularly occupied areas of the building. 

At the risk of making it sound too simple, daylighting design to achieve this credit point for LEED can be boiled down to three steps: 

1. Understanding the criteria

2. Using the software

3. Documenting the results. 

There are four options available:

Option 1: Simulation

Option 2: Prescriptive

Option 3: Measurement

Option 4: Combination of any of the above methods. 

The goal for any of these options is to achieve daylighting in 75% of the regularly occupied spaces. 

This article focuses on Option 1, the simulation method, defined by the USGBC as follows: 

  • Demonstrate through computer simulations that 75% or more of all regularly occupied spaces achieve daylight illuminance levels of a minimum of 25 fc and a maximum of 500 fc in a clear sky condition on Sept. 21 at 9 a.m. and 3 p.m.. Areas with illuminance levels below or above the range do not comply  However, designs that incorporate view-preserving automated shades for glare control may demonstrate compliance for only the minimum  25 fc illuminance level.
  • View-preserving shades are not part of the study in this article. 

Understanding the criteria 

Computer software: Physical models are an accurate way to evaluate the effects of daylighting and can be a cost-effective method of analysis. However, software programs are increasingly used to simulate and analyze daylighting effects.

Figure 1: An example of daylighting calculations are shown for 9 a.m. on Sept. 21. Courtesy: exp

Several daylighting software analysis programs can address factors such as window area, room floor area, window geometry, window height, and the visible light transmittance of glazing and factors such as orientation, room cavity ratios, visible angle to the sky, latitude designation, and interior room reflectance resulting in development of more sophisticated design strategies that demonstrate LEED compliance. 

In general, the USGBC does not endorse one software brand over another. Any software that can simulate based on the requirements listed in the rating system is acceptable. The rating system does require that the simulation be done under clear sky conditions. Some of the software products for daylighting analysis are AGi32, Radiance, Lumen Designer, and Daysim

Regularly occupied spaces: According to USGBC, "Regularly occupied spaces are areas where one or more individuals normally spend time (more than one hour per person per day on average) seated or standing as they work, study, or perform other focused activities inside a building." Some examples are private and open offices, conference rooms, break rooms, and lunch rooms. 

"Non-regularly occupied spaces are spaces that occupants pass through, or spaces used in pursuit of focused activities for less than one hour per person per day (on average)." Examples are hallways and foyers. 

"Non-occupied spaces are defined as spaces designed for equipment and machinery or storage with no human occupancy except for maintenance, repairs, and equipment retrieval." Examples of these include mechanical rooms, electrical rooms, storage areas, and restrooms. 

Sky conditions: In 2003, the International Commission on Illumination (CIE) adopted 15 standard skies that cover a broad spectrum of the usual skies found in the world. Each sky represents a unique sky luminance distribution, which is the most effective way to classify the 15 CIE Standard Skies. Most software brands use Illuminating Engineering Society (IES) and CIE-accepted sky models to calculate the sky’s distribution in the daylight calculations. LEED requires calculations to be done on a clear sky condition (see sidebar “Things to keep in mind” linked below).

Illuminance: Output of the simulation model shall show the illumination level range of 25 to 500 fc on a clear sky condition on Sept. 21 (Equinox), 9 a.m. and 3 p.m. Footcandles shall be measured at 30 in. above the floor (desk height). (In the past, LEED required daylighting calculations to be done at noon, but now they are done at 9 a.m. and 3 p.m. when solar positions are “lower” in the sky, which help projects claim credit point because daylight should penetrate more deeply into the building.) 


<< First < Previous 1 2 3 Next > Last >>

No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.