University of Oregon: Central Heat and Power Plant

Existing building retrofit, new construction; University of Oregon: Central Heat and Power Plant; Wood Harbinger

08/15/2013


Control room at University of Oregon central heating plant. Includes fully integrated Wonderware control system. Courtesy: Wood HarbingerEngineering firm: Wood Harbinger
2013 MEP Giants rank:
67
Project:
University of Oregon: Central Heat and Power Plant
Address:
Eugene, Ore., United States
Building type:
School (college, university)
Project type:
Other
Engineering services:
Automation & Controls, Code Compliance, Electrical/Power, Fire & Life Safety, HVAC, Lighting
Project timeline:
August 2008 to October 2012
Engineering services budget:
$300,000
MEP budget:
$1.9 million

Challenges

One of the main challenges encountered was to efficiently aid the University in developing major goals and a direction for the project. The University knew their systems for chilled water, power and steam were not meeting the current and future demands of the campus. The existing plant was using the water from the nearby Mill Race Stream for refrigeration equipment cooling which made maintenance incredibly time-consuming for plant operators. The Central Power Station (CPS) boiler plant had outlived its equipment life and the steam distribution system was becoming inadequate to deliver required steam to the campus. The electrical distribution system was also under capacity and needed expansion of a credible backup system.

The University’s stated goals for the project also presented challenges in itself. The State of Oregon required increased efficiency, redundancy in all systems, green design, and ease of system maintenance. Due to the nature of the original 1949/1964 steam plant building layout and structure, additional challenges arose with the construction and installation of the co-generation system. The first was limited space. The new system, which needed to provide twice the capacity along with a 2-story office complex, had to fit within the original steam plant structure. The building also had hollow floors, making it impossible to surround the new steam-turbine generator with concrete slabs to reduce external vibrations. Additionally, we discovered that over the past few decades as the University grew, the chilled water system connections varied from building to building causing disturbances with distribution system pressures and temperatures.

The University, additionally, needed the Central Power Station to maintain 24/7 operating 365 days a year and not disrupt campus life during the upgrade process.

Finally, the Central Power Station not only needed to provide heating and cooling services to meet the current campus demands but also last through the next 40 years of campus growth.

Solutions

Wood Harbinger’s engineers tackled these challenges by leading a multi-day design charette with the design team, key stakeholders from the University, adjacent lease-hold property owners, and local utility district. The team listened and discussed each concern to gain a clear understanding of the University’s needs and expectations.

After a series of studies and investigations, including performing thermal load analyses, evaluating condition and capacity of over 24,000 ft of campus-wide tunnels, and investigating water system connections; the team developed design options for the new Central Power Station. They increased efficiency by having the co-generation unit follow steam load instead of electrical load, as well as having a plate and frame heat exchanger in the chilled water system provide “free cooling” for minimal cooling demand. The new system was able to increase steam pressure by utilizing an existing 12 in. – 20 psi steam header, increased distribution pressure to 60 psi, which required changing pressure regulators at each of the over 100 buildings – resulting in a significant increase in capacity. This overall system was also able to lower the boiler operating pressure from 225 to 150 psi, to increase boiler efficiency. Additionally, the chilled water plant was designed for expansion by including room for six future cooling towers, two future chillers, and a fourth standby generator.

To provide consistency and ease future maintenance of the new system, we helped discover the best connections for the chilled water distribution system and standardized this across the whole campus. We also wrote specifications to ensure that future installations would comply with the new standards.

To address the issues of budget, we assisted the University by defining the project and budget for their use in a presentation for State Legislation, which was ultimately successful. Additionally, we reused existing infrastructure whenever possible, saving approximately $2 million.

The team also designed a bar coding system to simplify maintenance, repair and replacement, where a simple scan would deliver the history, specifications, and function of any piece of equipment. Additionally, they created a hydraulic model of the entire campus chilled water system to assist in future modifications as the University grew. A phasing plan was used that allowed for 95% of the equipment to be installed while keeping the campus functional.

The electrical engineers designed switching configurations that eliminated power outages on the campus during construction. They also provided mathematical modeling of the entire system. This required a transient analysis, or swing-curve analysis, to predict the performance of each component so that specific settings of the protective relays and programming of the sequence of operations could be established.

Overall the team met the all the goals of the University through increasing efficiency, adding redundancy to all systems, and gaining operational cost savings. The chilled water system alone exceeded the required state energy code by 18%, garnered a $900,000 rebate from the local utility, and reduced the University’s carbon footprint by 7%. All these solutions helped achieve the University’s goals of minimal campus disruption and of having a Central Power Station that would fulfill their needs until 2049.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.