Scoping automation and control projects

A decision to leverage the relatively small cost of a quality scope and solid conceptual design can create significant long term savings and achieve an optimum solution.

10/22/2012


The approach taken during front-end engineering feasibility studies and scope development frequently determines whether an industrial control project will be successful. Unfortunately, budgetary and timing constraints normally limit the approach and resources used during these critical phases of project development, which ultimately result in unanticipated costs, technical complications, and schedule delays during subsequent project implementation. 

For example, plant operations or maintenance personnel are routinely tasked with developing project scopes and capital budget estimates in a short period of time while continuing to support on-going, day-to-day plant operations. 

In such situations, operations or maintenance personnel often have little choice but to build a total installed cost (TIC) estimate based primarily upon budgetary quotations for major equipment (based themselves upon minimal, if any, technical requirements specification) but with minimal time allocated to all other aspects of the project’s TIC.

Although this approach can be good for initial project evaluation and preliminary screenings, when capital budget allocations and schedules are based upon such estimates, the following types of challenges tend to develop during project implementation:

• Compliance with detailed codes and technical design standards introduce costs and/or delays.
•  Strategic alternatives for truly optimum solutions, such as different technologies, creative implementation tactics, or other vendors’ product offerings, are not discovered until too late in the project schedule, typically after long-lead equipment has already been ordered and detailed design has started.
• Subtle, often unknown, technical design assumptions implicit in the original plan are proven invalid and result in costly changes or delays during implementation.
• Constructability, operability, or maintenance concerns are expressed in late stages, frequently during well-intentioned project reviews after detailed design has progressed and budgets have been established.

On the other hand, if you want to maximize your project success, here are some useful techniques:

• Leverage the relatively small cost of a quality scope and solid conceptual design to realize significant long term savings and achieve an optimum solution.
• Be confident that that the conceptual design basis for the estimate is based upon a workable solution.
• Identify any implicit, hidden, or critical technical assumptions in the conceptual design worthy of confirmation.
• Manage (reduce) the project scoping cost by making realistic but conservative assumptions regarding generally known or established details that are not likely to introduce unexpected costs or delays.
• Consult external resources that can fully commit to scope development under the direction of plant personnel who can then better support on-going operations while offering key objectives and insight.
• Work closely and collaborate with such external resources on a time and material basis so the external resources will be encouraged to offer a variety of alternatives for consideration by plant personnel.
• Review the conceptual design with operations, maintenance, and construction personnel before finalizing the capital budget.
• Leverage prior experiences and lessons learned of all available resources.
• Anticipate the effort required to analyze and address the additional level of numerous details as required during the transition from an “80% design” to a “100% design.”

With few exceptions, the incremental cost for a solid project scope and estimate will (a) yield a positive net present value to the project’s overall TIC and (b) be recovered during a more efficient and effective detailed design and development process as a result.

This post was written by Shane Hudson. Shane is principal engineer at MAVERICK Technologies, a leading system integrator providing industrial automation, operational support and control systems engineering services in the manufacturing and process industries. MAVERICK delivers expertise and consulting in a wide variety of areas including industrial automation controls, distributed control systems, manufacturing execution systems, operational strategy, and business process optimization. The company provides a full range of automation and controls services – ranging from PID controller tuning and HMI programming to serving as a main automation contractor. Additionally MAVERICK offers industrial and technical staffing services, placing on-site automation, instrumentation and controls engineers.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.