MRO storeroom best practices - are you kitting me?

The storeroom is an integral part of an efficient and effective maintenance process. Equipment reliability, uptime, and frontline productivity rely on having the right spare parts and tools available in the right quantity when the work order is scheduled.

07/27/2011


 

By Andy Gager, Director Consulting Serivices, Marshall Institute


The storeroom is an integral part of an efficient and effective maintenance process. Equipment reliability, uptime, and frontline productivity rely on having the right spare parts and tools available in the right quantity when the work order is scheduled. That's why having the correct tactical and strategic processes in place can turn your storeroom into a profit center. Today we are going to focus on kitting, one of the key tactical processes. Kitting is the process of identifying and preparing - in advance - the material and tools required to successfully execute the work order in the least disruptive manner. Effective kitting requires other key maintenance systems such as planning, scheduling, and an established PM program to be in place. The main benefit of kitting is increasing productivity through greater wrench time and limiting downtime by purging non-valued activities. In a typical organization 18% of a technician's time is spent looking for parts and another 24%-26% is walking to and fro the job site. If you haven't experienced it yourself, I'm sure you have seen techs and craftspeople make multiple trips to the storeroom looking for what they need to finish the work.

Below is an ideal kitting process for effective work execution; however it assumes that supporting systems are in place.

— Attain high storeroom credibility (i.e. inventory accuracy).
— Locate all materials and tools for the work order.
— Place them in a designated "staging" area.
— The staging area must be secure, organized, and kits easily retrievable.
— Once scheduled, the kit may then be transferred to the site prior to the event so that the craftspeople have all they need to complete the work order.
— Review all closed and unfulfilled orders for materials used, returned, work order rescheduling, job close out, etc.

If you are not currently following this kitting process then look for a quick win such as identifying a staging area in the storeroom where you can begin kitting. The easiest of work orders to start are the regularly scheduled PM work orders. I suggest piloting a specific area to start. Debug the process and then roll out to other areas.

To truly be an effective storeroom you must operate as one within all manufacturing processes, production, planning, scheduling, operations, etc. To become the most effective organization, engage others in your efforts to become more effective. After all, although we all have sub-goals and objectives we are all working towards a common organizational goal.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. The 2012 Top Plant winners have been named.
In 2012, Plant Engineering's Product of the Year program will celebrated its 25th anniversary. Read about the 2012 winners and nominate for 2013.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2012 Leaders here.
Investment in excellence: One plant's improved productivity and quality was repaid when their company expanded the facility
Strategic uptime, Increased capacity goes right to the bottom line
2013 Forecast Issue: A shift in manufacturing
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Alarm management tips, Power management, Building automation
Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Attacking Energy Costs: Strategies for showing financial return on energy management investments

2012 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.