Metering, monitoring feedwater systems

One of the most common misunderstandings sees in boiler water treatment programs is the confusion surrounding the measurement of condensate return and the correct configuration and dosing point for chemical injection.

09/18/2013


One of the most common misunderstandings sees in boiler water treatment programs is the confusion surrounding the measurement of condensate return and the correct configuration and dosing point for chemical injection.

How to determine condensate return

The amount of condensate return is an important aspect of understanding the water/steam relationship of any steam generating plant. From a water treatment perspective, it determines the cycles of concentration, the level of make-up dilution and therefore the untreated quality of feed water.

Mass balance equation: FW = MU + CR

By placing meters on the make-up (MU) and feedwater (FW) pipelines, we can quickly determine the amount of condensate return by mass balance.

When combined with steam metering (S) we can also determine the blow down rate (BD) of the boiler.

Mass balance equation: FW = S + BD

These two critical parameters determine the level of chemical dosing required and the adequate level of blow down, and the estimated chemical consumption and therefore cost of the program.

Chemical dosing—where and how?

Now that we can quantify the chemical demand of the feed water with adequate metering, where do we dose the chemicals? The chemical dosing point can be a complicated decision based on the sophistication of pre-treatment plant and the nature and number of chemicals used. For this discussion we will restrict our interests to simple feed tank (no economizer or deaerator) and simple chemical programs based on oxygen scavenger, alkalinity and non sequestrant inhibitors. This would adequately represent 90% of industrial steam plants.

Ensure that the chemical containing oxygen control is dosed close to the feed water outlet at the feed tank away from incoming make-up water agitation. The most common mistake is to dose this chemical into the middle or upper part of the feed tank, this results in inadequate corrosion protection of the boiler, or excessive chemical use. For the preferred two- to four-pump system, depending on the chemistry, most scale inhibitors and alkalinity agents may be dosed in the feed line. There are no one-drum programs that outperform the multi pump alternatives.

Content provided by Spirax Sarco, originally published in Steam News Magazine.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.