Machine-mount IP67 I/O will initially cost more than IP20. However, thanks to the ease of installation and the potential for reducing the number of cabinets, it can save money in the long run. Courtesy: Phoenix ContactControl system wiring, at input/output (I/O) connections, can be among the most challenging (and perhaps most feared) of upgrades. When replacing I/O connections, what are key considerations? Jason Haldeman, Phoenix Contact product marketing lead specialist for I/O, offered answers. When replacing or upgrading I/O modules, consider documentation, controllers, application needs, and support.

Q: Control Engineering: Is there documentation?

A: Jason Haldeman, Phoenix Contact product marketing lead specialist for I/O: Good documentation is very important at all stages of I/O installation. You count on documentation to help with the upgrade. If you don’t know what you have, it will be much more difficult to upgrade your connections. Your supplier should have all the proper supporting documentation to simplify the I/O installation.

CE: What network protocols are required and will they be wired, wireless, serial, digital, or a combination?

Haldeman: Choosing the desired bus network is very dependent on the PC/PLC used in your current system. These suppliers provide interfaces to specific networks, limiting your options and locking you into specific networks. Moving away from their PC/PLCs would require rewriting your entire control program. For this reason most people stick with what they are comfortable programming, dictating what I/O network they use (for example, DeviceNet, Profibus, Interbus, Modbus RTU, EtherNet/IP, Profinet, and Modbus/TCP). Most new application are moving to Ethernet protocol, providing greater flexibility to incorporate options like redundancy and wireless.

CE: What functionality do attached applications need to integrate? What types of signals (analog, digital, serial, mixed...), what units (current, volts, resistance, AC, DC...), what range, and how many channels are needed? What are the sensing, signal conditioning, distributed control, isolation, and other requirements?

Haldeman: Questions like this make it very important for you to select an I/O provider that meets the flexibility your application demands. Your provider should be able to supply you with a wide, modular range of inputs, outputs, special functions, integrated wireless communication, and connectivity to fieldbus and industrial Ethernet networks. On top of your I/O needs, the supplier should be able to supply all the supporting components, such as power supplies, Ethernet switches, and terminal blocks.

CE: Will the application expand and by how much?

A variety of input/output modules are available in the Phoenix Contact Inline and Fieldline I/O systems for IP20 control panel use or for an IP67 machine mount application. Phoenix Contact Inline Block IO are shown. Courtesy: Phoenix ContactHaldeman: Modular I/O systems allow the user to custom-configure an I/O station to meet their exact application needs. In the future, if you need more I/O, you simply purchase additional I/O points and attach them to your existing I/O station.

CE: Will the I/O connections be enclosed or exposed?

Haldeman: This is a very important part of your decision-making. Do you use IP20 I/O inside a cabinet or lose the cabinet and go with IP67 I/O mounted directly on the machine? IP67 I/O initially costs more, but saves you with ease of installation and the cost saving of not having as many cabinets.

CE: What are among the most-overlooked considerations?

Haldeman: Support is a topic that is always overlooked until it is needed. Your I/O provider needs to be able to supply the necessary support functions to assist with questions during the installation of the I/O modules.

- Jason Haldeman, Phoenix Contact product marketing lead specialist for I/O, and Mark T. Hoske, CFE Media, Control Engineering, www.controleng.com

www.phoenixcontact.com



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.