Innovative hydraulic lift system builds 156-ft diameter, free-standing grain bin

Application Update: Said to be the world's largest, the bin's building methods are the result of a four-company collaboration, and new design and control methods - October Control Engineering.

09/27/2010


Combining innovations in controls and hydraulics into a system of jacks that could communicate wirelessly, an engineering partnership enables the building of grain bins to take a giant step forward.

In Brainard, NE, EAD Control Systems, LLC has partnered with RC Hydraulic Systems, Lowe Construction, Inc. and Brock to erect the world’s largest free-standing grain bin. This bin has a 156 ft diameter, holds 1.3 million bushels, and stands without a center structured support.

EAD Control Systems and RC Hydraulic Systems utilized three years of research, design and continual testing of hydraulic jacks to devise a lift system that could build such a bin. The objective of the research was to produce a self-contained system that decreased the cords and cables used during the lifting process in order to speed up construction while ensuring the safety of the crew and grain bin. 

EAD Control Systems and RC Hydraulic Systems designed the system of hydraulic jacks, which are manufactured locally.  Lowe Construction is the only company erecting grain bins of this magnitude, and Brock is the only company manufacturing free standing bins.

During testing, one jack held 48,000 lb. A common 90-ft diameter grain bin typically requires 50 jacks during construction; the self-contained system of hydraulic jacks invented by the team requires fewer than 20 jacks, saving space and materials. For the 156-ft diameter bin, 30 hydraulic jacks were used and collectively they were able to support more than 905,000 lb. 

All of the control panels, wireless and hardwired, function off of a main operator panel system that monitors every jack’s status.  This includes weight load and height to ensure proper functionality. The weight on each jack is evenly distributed, while the height stays within the targeted parameters. 

The building process

The building of the record-setting grain bin began with a concrete foundation supported by 276 concrete columns to a depth of 70-ft to ensure proper stability. Lowe Construction, with materials provided by Brock, constructed the 300,000-lb roof, which is built on the foundation. Jacks are then set in place on the interior of the roof as close to the wall as possible. The jacks are then bolted to the concrete floor of the bin. 

Once everything is in place, the jacks are bolted to the first ring of the grain bin, which is attached to the roof. A computer automatically sets the jack heights then raises the entire bin to an exact predetermined height. Lowe Construction then bolts another ring to the first ring. Once the second ring is completed, the jacks are unbolted from the first ring, lowered automatically by the computer, then bolted to the second ring, ready to lift the bin again. The process is then repeated until the structure reaches the desired height.

It takes only four to five minutes for the hydraulic jack system to go full stroke or complete a full lift. Because grain bins are susceptible to strong winds during construction, the fast stroke time reduces the risk of the bin tipping over, therefore making it safer for the workers.

www.eadengineering.com/our-projects.html

EAD Engineering

Also see Control Engineering areas on

Motors and Drives;

Machine Control; and the

Machine Safety blog.


- Edited by Renee Bassett for Control Engineering, www.controleng.com.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.