Flats East, LLC Mixed Use Development

New construction: Flats East, LLC Mixed Use Development; Thorson Baker and Associates Inc.


East Bank office tower lobbyProject name: Flats East, LLC Mixed Use Development

Location: Cleveland, Ohio

Firm name: Thorson Baker and Associates Inc.

Project type, building type: New construction, office

Project duration: 2 years

Project completion date: December, 2012

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $43.5 million

Engineering challenges

The Flats East Mixed-Use Development Project is located on the waterfront, directly in the heart of the East Bank. The addition of this multi-use building to the city of Cleveland will act as a platform for new development of restaurants, hotels, retail, sporting events, recreational activities, and nightlife. Based on the project’s location, this destination will merge many forms of entertainment and provide an attraction for local and out-of-town guests.

Main electrical vault under construction Flats East BankThis $145,000,000+ project consists of approximately 820,000 sq ft of mixed-use space, including three stories of parking podium (approximately 225,000 sq ft) supporting a 19-story high-rise office tower (approximately 450,000 sq ft) and eight stories of high-rise hotel (150 rooms), restaurants, and fitness (approximately 120,000 sq ft). Three major tenants for this project include the Aloft Hotel, Ernst & Young, and Tucker Ellis. This is a registered U.S. Green Building Council LEED V3 project, targeting LEED Silver certification, and reinforces the Thorson Baker and Associates Inc. (TBA) experience in sustainable design.

Seventeen additional TBA projects have received LEED certification and 40 additional projects are registered and on track to receive certification. The design process started with TBA working for the architect, directly for the owner in a design-assist process along with the construction team, including the MEP prime subcontractors. Initial indications were that the project was $30 million over the project budget, so the design team had to come up with an effective solution to meet the needs and goals for the project.

15th-floor view of Cleveland skyline from the Office Tower FlatsSolutions

A few months into the design process, the delivery method changed to a GMP (guaranteed maximum price) process, where the MEP contractors were bid and locked into a GMP based on 50% complete construction documents. The $30M budget gap was closed and allowed the project to successfully move forward. Once the construction team was finalized, TBA was contracted through the architect to work as a team for the construction manager to complete the construction documents and follow through with construction administration. TBA has been able to successfully manage the expectations of both clients throughout the process while maintaining the integrity of the design with no increase in construction cost. 

Exterior elevation under construction Flats East BankMain mechanical room HVAC piping isometric diagram Flats East Bank

No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
A cool solution: Collaboration, chemistry leads to foundry coat product development; See the 2015 Product of the Year Finalists
Raising the standard: What's new with NFPA 70E; A global view of manufacturing; Maintenance data; Fit bearings properly
Sister act: Building on their father's legacy, a new generation moves Bales Metal Surface Solutions forward; Meet the 2015 Engineering Leaders Under 40
Cyber security cost-efficient for industrial control systems; Extracting full value from operational data; Managing cyber security risks
Drilling for Big Data: Managing the flow of information; Big data drilldown series: Challenge and opportunity; OT to IT: Creating a circle of improvement; Industry loses best workers, again
Pipeline vulnerabilities? Securing hydrocarbon transit; Predictive analytics hit the mainstream; Dirty pipelines decrease flow, production—pig your line; Ensuring pipeline physical and cyber security
Upgrading secondary control systems; Keeping enclosures conditioned; Diagnostics increase equipment uptime; Mechatronics simplifies machine design
Designing positive-energy buildings; Ensuring power quality; Complying with NFPA 110; Minimizing arc flash hazards
Building high availability into industrial computers; Of key metrics and myth busting; The truth about five common VFD myths

Annual Salary Survey

After almost a decade of uncertainty, the confidence of plant floor managers is soaring. Even with a number of challenges and while implementing new technologies, there is a renewed sense of optimism among plant managers about their business and their future.

The respondents to the 2014 Plant Engineering Salary Survey come from throughout the U.S. and serve a variety of industries, but they are uniform in their optimism about manufacturing. This year’s survey found 79% consider manufacturing a secure career. That’s up from 75% in 2013 and significantly higher than the 63% figure when Plant Engineering first started asking that question a decade ago.

Read more: 2014 Salary Survey: Confidence rises amid the challenges

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.