Flats East, LLC Mixed Use Development

New construction: Flats East, LLC Mixed Use Development; Thorson Baker and Associates Inc.

08/09/2012


East Bank office tower lobbyProject name: Flats East, LLC Mixed Use Development

Location: Cleveland, Ohio

Firm name: Thorson Baker and Associates Inc.

Project type, building type: New construction, office

Project duration: 2 years

Project completion date: December, 2012

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $43.5 million

Engineering challenges

The Flats East Mixed-Use Development Project is located on the waterfront, directly in the heart of the East Bank. The addition of this multi-use building to the city of Cleveland will act as a platform for new development of restaurants, hotels, retail, sporting events, recreational activities, and nightlife. Based on the project’s location, this destination will merge many forms of entertainment and provide an attraction for local and out-of-town guests.

Main electrical vault under construction Flats East BankThis $145,000,000+ project consists of approximately 820,000 sq ft of mixed-use space, including three stories of parking podium (approximately 225,000 sq ft) supporting a 19-story high-rise office tower (approximately 450,000 sq ft) and eight stories of high-rise hotel (150 rooms), restaurants, and fitness (approximately 120,000 sq ft). Three major tenants for this project include the Aloft Hotel, Ernst & Young, and Tucker Ellis. This is a registered U.S. Green Building Council LEED V3 project, targeting LEED Silver certification, and reinforces the Thorson Baker and Associates Inc. (TBA) experience in sustainable design.

Seventeen additional TBA projects have received LEED certification and 40 additional projects are registered and on track to receive certification. The design process started with TBA working for the architect, directly for the owner in a design-assist process along with the construction team, including the MEP prime subcontractors. Initial indications were that the project was $30 million over the project budget, so the design team had to come up with an effective solution to meet the needs and goals for the project.

15th-floor view of Cleveland skyline from the Office Tower FlatsSolutions

A few months into the design process, the delivery method changed to a GMP (guaranteed maximum price) process, where the MEP contractors were bid and locked into a GMP based on 50% complete construction documents. The $30M budget gap was closed and allowed the project to successfully move forward. Once the construction team was finalized, TBA was contracted through the architect to work as a team for the construction manager to complete the construction documents and follow through with construction administration. TBA has been able to successfully manage the expectations of both clients throughout the process while maintaining the integrity of the design with no increase in construction cost. 

Exterior elevation under construction Flats East BankMain mechanical room HVAC piping isometric diagram Flats East Bank



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.