Effective task planning can optimize your outage

Outages can only be successful when the outage work is planned effectively before the work is scheduled and/or started.

03/12/2010


By Tim Kister, Life Cycle Engineering.

We are all aware of the impact outages have on business. In many cases as much as one third to one half of the maintenance budget is consumed during this timeframe. Factor in the cost of lost production during this time and the costs are tremendous. To offset the cost of lost production and the cost of maintenance we have to maximize the amount of work accomplished in the shortest amount of time, yet at the same time be effective in what work is performed and how it is managed.
Outages can only be successful when the outage work is planned effectively before the work is scheduled and/or started. There are four areas of planning that are often overlooked or ineffectively addressed: determining outage tasks, defining task scope, identifying task hazards and/or obstacles, and completing task planning completion.
The objective of an outage should be to accomplish the identified tasks with a high level of precision, so that equipment and or processes restart with minimal problems or scrap losses, and operations will have the confidence that equipment and processes will operate at desired rate and quality until the next scheduled outage. Outage planning's objective is to minimize the impact of delays, waiting, obstacles and bottlenecks during work execution to allow on-time completion of work and on-time equipment/process startup while managing outage planned costs within the outage budget.
When a facility decides to identify major outage work far in advance, and the work is carefully planned to maximize ease of execution, the result will be lower costs. It is vitally important that the outage work list be kept as short as possible. Keeping the list short is both the means to reduce costs and the primary method of focusing on work that can only be performed during a major outage.

Here is a suggested planning timeline:
3 to 10 years out Rough work list developed
18 to 24 months out Work list reaches the budget,
planning begins
12 months out Monthly outage meetings begin
6 months out Work list is locked down. Planning
is 90% complete
0 month Outage occurs; all work is planned
and scheduled
1 month post outage Post-outage critique meetings occur
Successful maintenance organizations identify their outage work list from various sources, all of which should be in alignment with the outage objectives. These sources include:

  • Work requests generated as a result of the post-outage critique meetings
  • Regulatory issues
  • Outage and equipment history
  • PM/PdM activities, backlog or carryover work from previous outages.
    • The planning process can commence once the outage work list has been established and approved. Successful outage planning and scheduling depends on important events, including identifying work tasks, occurring far in advance.
      Lock down the list
      Locking down the work list six months prior to the outage is essential to effectively managing and planning outage work. Without a lockdown there will be a never-ending flood of last-minute unplanned work items, resulting in excessive costs, reactive response and increased probability of outage schedule overrun. Part delivery issues and labor availability become a problem when work is added after the lock down date. Some individuals may find a lockdown process difficult to accept.
      A process to address add-on outage work must be developed and in place that requires the requestor to justify the need and identify what existing work items will be sacrificed. Management must enforce the lockdown time frame and gain agreement from all parties that it will be followed. Remember that planning work is expensive. It is extremely wasteful to cancel a job that is already planned (with parts on order or onsite), in order to do unplanned work.
      As outage tasks are identified, the task scope has to be defined. Without a defined scope, workers are left to determine the scope based on their knowledge, which may not be the intended scope at all. This often results in inefficiencies, delays and costly overruns. If the following questions are answered, a clear work scope will result:

      • Does the work request adequately define what the task expects to accomplish?
      • Does the task have a specific starting and ending point?
      • Will this require meeting testing or acceptance criteria?
      • Will the task impact health, safety or environmental aspects?
      • Who will have the final say on the priority of the work?
        • As a part of defining the scope of work, the planner will be required to conduct site visits at the location of the requested work to determine the five basic elements of work planning:

          • The labor requirements (how many, skills, how long) for the task
          • The specific location of the work (asset and physical location)
          • When the work needs to happen (sequence in the scheduling process)
          • The materials, tools and equipment to perform the work
          • The information, specifications, safety, permits required.
            • To accomplish this level of planning it is very important that adequate personnel be dedicated full time to the planning of outage work packages.
              Value of site visits
              Site visits are essential to effective outage planning. The identification of job hazards, safety issues and obstacles that impact job progress is often overlooked. All can be avoided or taken into account if addressed during the planning process. Some of the most common items include the complexity of the lockout/tag out, permit requirements (line breaks, confined space, excavation and building permits), air and water discharges, barricade requirements (will the barricaded work area interfere with normal traffic patterns) and whether the work site will support equipment weight and height requirements.
              As the planning process approaches the six month cutoff date, work packages should be fully planned and usually waiting on identified parts and materials to arrive. These questions can help determine if the planning process is complete:

              • Is the scope of work concise and easily understood?
              • Have all aspects of the task have been evaluated and addressed?
              • Have the job hazards, safety, permit requirements and potential obstacles been identified, addressed and communicated?
              • Does the task sequence make sense, is the methodology defined, and does it include special instructions, specifications and testing/quality checks?
              • Have all determinable material, parts, tools and equipment requirements been addressed and actions taken to provide the necessary items with delivery within the prescribed "need by" dates?
              • Have the specific work groups been identified and task steps been coordinated to minimize non-value effort?
              • Have realistic labor estimates and labor resource requirements been established?
              • Do all work packages include all supporting documentation, prints, schematics and pictures?
                • Outage management is an effective tool for reducing costs and increasing plant productivity. When the decision is made to identify major outage work far in advance and then carefully plan the work for maximum ease of execution, the result will be lower costs.
                  If, at the same time, disruptions to the process (such as late add-on work) are kept under control, there will be sufficient resources available to continually refine and improve the outage model for even greater savings.

                  Tim Kister is a Planning and Scheduling Subject Matter Expert at Life Cycle Engineering. A dedicated educator, Tim has facilitated more than 100 workshops and seminars focused on maintenance management and planning & scheduling, and has co-authored the book "Maintenance Planning and Scheduling Handbook; Streamlining Your Organization for a Lean Environment." You can reach Tim at tkister@LCE.com.





No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Your leaks start here: Take a disciplined approach with your hydraulic system; U.S. presence at Hannover Messe a rousing success
Hannover Messe 2016: Taking hold of the future - Partner Country status spotlights U.S. manufacturing; Honoring manufacturing excellence: The 2015 Product of the Year Winners
Inside IIoT: How technology, strategy can improve your operation; Dry media or web scrubber?; Six steps to design a PM program
Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Digital oilfields: Integrated HMI/SCADA systems enable smarter data acquisition; Real-world impact of simulation; Electric actuator technology prospers in production fields
Special report: U.S. natural gas; LNG transport technologies evolve to meet market demand; Understanding new methane regulations; Predictive maintenance for gas pipeline compressors
Warehouse winter comfort: The HTHV solution; Cooling with natural gas; Plastics industry booming
Managing automation upgrades, retrofits; Making technical, business sense; Ensuring network cyber security
Designing generator systems; Using online commissioning tools; Selective coordination best practices

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
This article collection contains several articles on the vital role that compressed air plays in manufacturing plants.
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
This article collection contains several articles on strategic maintenance and understanding all the parts of your plant.
click me