Designing a time synchronization source

A challenge in designing a substation is to time synchronize all connected devices, which requires proper design.

By Sam Sciacca

10/02/2012


A well-known challenge in designing a substation is to time synchronize all connected devices, which requires proper design. A closely related challenge, and the topic of next week's blog, arises in understanding how vendors use time synchronization signals and what accuracy and resolution they provide in their devices. Both of these topics are the subject of current standards efforts.

 

In the design of a large industrial substation, particularly one that interfaces with an electric utility at transmission voltage levels, it's often necessary to know the precise time and sequence of events. That's critical to determining whether protection and command-and-control elements in the industrial substation functioned properly.

 

"Sequential event reporting" allows the engineer or the substation owner to evaluate whether all protection events occurred as designed. If events didn't occur as expected, sequential time reporting provides the basis for a design or engineering review. Thus the consulting specifying engineer has to determine the appropriate selection and distribution of a time source.

 

Different time sources and distribution methods are available, and they all have to do with the degree of accuracy needed in the system. So it's important for the consulting specifying engineer to understand the limitations of each of those systems, and to determine whether they provide the degree of accuracy needed in a specific application.

 

For a substation interconnected to the utility at a distribution level, accuracy in the range of 10 to 20 milliseconds may be sufficient. Systems are available that can provide this accuracy through a local, master clock provided at the industrial facility, or through the utility via protocols, such as IEEE Standard 1815 or simple network time protocol (SNMP). Simply connecting intelligent electronic devices (IEDs) with IEEE 1815 or SNMP will provide time synchronization at that level.

 

When time synchronization requires a resolution of, say, +/-1 millisecond, typically an external time source is needed. That external time source could be either a GPS receiver or a WWV receiver. GPS uses the very accurate time signals from a global satellite system, and WWV broadcasts a radio signal sent from an atomic time clock source maintained by the National Institute for Science and Technology (NIST) in Fort Collins, Colo. (Background on the WWV system is found here.)

 


Because it would be cost-prohibitive to equip every substation IED with its own receiver for either GPS or WWV, the consulting specifying engineer must properly design the distribution of the time source signal so it doesn't degrade and lose its resolution. One common mechanism for distributing the signal is a protocol known as IRIG-B, or Inter-Range Guidance and Instrumentation. It's a standard first designed for the military to correlate time data when testing weapon performance.

 

The third level of accuracy is in the microsecond range. Typically, this range of resolution is not required at the industrial level, with the exception of facilities injecting large amounts of power back into the grid. In that case, the design of the interface to, say, a large wind power plant or a co-generator-any facility that can introduce megawatts (versus kilowatts) into the transmission network-increasingly includes higher accuracy devices such as synchrophasors.

 

Synchrophasors require a higher degree of accuracy in the time source clock. So, again, the consulting specifying engineer needs to look carefully at each device he's specifying to ensure that degree of accuracy and also at the design of the physical system that distributes that signal to all the devices that need it. Time sources in this range of accuracy will need to comply with IEEE 1588, Standard for a Precision Clock Synchronization Protocol for Networked Measurement and Control Systems, and IEEE C37.238, Standard Profile for Use of IEEE Std. 1588 Precision Time Protocol in Power System Applications.

 

The proper distribution of time signals at high resolution begins with hard-wired connections and the proper cables, the proper wiring practices, for all the physical interfaces to the devices. For network based distribution systems, the design/specification of the network, including switches, routers, and configuration of these devices will also need careful consideration. For signals distributed wirelessly, the consulting specifying engineer needs to look carefully at the specifications on the receivers, so that he does not design a distribution system for the signal that actually degrades the signal.

 


Sam Sciacca, PE, senior member of IEEE, president of SCS Consulting LLC, Winsted, Conn.Sam Sciacca is an active senior member in the IEEE and the International Electrotechnical Commission (IEC) in the area of utility automation. He has more than 25 years of experience in the domestic and international electrical utility industries. Sciacca serves as the chair of two IEEE working groups that focus on cyber security for electric utilities: the Substations Working Group C1 (P1686) and the Power System Relay Committee Working Group H13 (PC37.240). Sciacca also is president of SCS Consulting.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. The 2012 Top Plant winners have been named.
In 2012, Plant Engineering's Product of the Year program will celebrated its 25th anniversary. Read about the 2012 winners and nominate for 2013.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2012 Leaders here.
Find the fake! Counterfeit electrical equipment a clear and present danger
Investment in excellence: One plant's improved productivity and quality was repaid when their company expanded the facility
Strategic uptime, Increased capacity goes right to the bottom line
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Alarm management tips, Power management, Building automation
Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Attacking Energy Costs: Strategies for showing financial return on energy management investments

2012 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.