Atmel advances risk assessment

Staff -- Plant Engineering, 4/1/2003

Two Atmel Corp. semiconductor manufacturing plants in Colorado Springs, CO, operate 24 hr/day, 7 days/week. Any interruption to the manufacturing process can cost from several hundred thousand to several million dollars in lost revenues. As a result, it is imperative that manufacturing support systems be fully functional with minimal downtime.

Aging facilities and equipment coupled with an increasingly severe resource-constrained environment created a need to assess the overall risk associated with individual facilities systems.

To meet the challenge, Atmel formed a task team composed of facility engineers and operations and maintenance technicians. The team first identified seven risk factors that contributed to or helped eliminate risk:

  • Overall priority of the system as it relates to mission impact
  • Facility system or utility capacity rating
  • Facility system or utility redundancy
  • System documentation, including as-built drawings and system labeling
  • Level of controls and/or alarms monitoring the system
  • Facility system or utility spare parts availability
  • Operational procedures and training.

Each factor was assigned a weight relative to its contribution to risk, and an algorithm was calculated for linking the factors. Using a 100-point scale, each system could then be categorized as having a low, medium, or major Risk Assessment Grade.

A Microsoft Access database was developed for tracking all of the data as well as numerous comments for each system.

Final step in the risk assessment process is a review of all data by facilities engineering and operations managers along with the appropriate facilities engineers. Managers decide whether to accept the rating according to the numerical scheme or to flag a system with a lower or higher risk rating. In any case, all of the original data is retained in the database.

Through a concentrated effort of system data collection and analysis, Atmel has developed a comprehensive, prioritized roadmap for reducing facilities system risk.

Email
Print
Reprint
Learn RSS

Talkback

We would love your feedback!

Post a comment

» VIEW ALL TALKBACK THREADS

Related Content

Related Content

 

By This Author

Sponsored Links



 
Advertisement
SPONSORED LINKS

More Content

  • Blogs
  • Podcasts
  • Photos

Blogs

  • Bob Vavra
    FIVE FAST THINGS

    September 16, 2008
    What do the Chinese know, and what can we learn?
    1. Reaching across a great wall: Members of the Chinese Machine Tool and Tool Builders’ Associ...
    More
  • Bob Vavra
    Five Fast Things

    September 2, 2008
    Getting competitive on energy, getting tough on immigration
    1. One way to get competitive: We’ve highlighted the growing solar panel business around the U...
    More
  • » VIEW ALL BLOGS RSS

Podcasts

Photos

  • 2007 Product of the Year Winners
    This year's Plant Engineering Product of the Year winners were honored at the Manufacturing Summit in Chicago.
  • Top Plant: GEMA
    The game plan for GEMA (Global Engine Manufacturing Alliance) focuses on best-in-class execution
  • Top Plant: SEW Eurodrive
    SEW Eurodrive builds a culture based on employee empowerment and continuous improvement.
Advertisements





NEWSLETTERS
Click on a title below to learn more.

Plant Engineering PlantMail!
Plant Engineering Hotwire
Plant Engineering Hotwire Automation
Plant Engineering Maintenance Connection
Plant Engineering Sustainable Manufacturing
©2008 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites